Here East
Client:
Laing O’Rourke
Market Sector:
Commercial
Services Supplied:
Toilet Cubicles
Download Case Study
Here East was a special project. Our team of 15 carpenters worked alongside main contractor Laing O’Rourke on this high-spec £100m conversion of the media centre for the 2012 London Olympics into a media building (including the studios for BT Sport) and huge IT centre. We undertook drylining, installed all the vinyl, high-end fixtures and fittings, bump rail, fitted out the toilets and did all the painting.
The quality of the fixtures and fittings was extremely high for Here East. Set against a backdrop of a modern, factory-style design with yellow doors, exposed pipework and an enormous football suspended from the roof. Detail was key, including stopcock-style coat hooks. We also had to re-source doors when the original supplier couldn’t fulfil the contract. We won Laing O’Rourke’s quality award for our work.